DDelivery — Urgent CountermeasuresNovember 2026

Urgent Countermeasures

Date IdentifiedLocationIssue DescriptionCorrective Action(s)Responsible to CompleteDue DateStatus
04/27/2026AgeExcessive in process queue timesReview queue times, reasons, and opportunities with operations teams.Lee S.07/31/2026In Progress
04/27/2026QuenchHot water recovery timeDMC to install new boiler and test by 5/13Lee S. / DMC / Omar05/13/2026Complete
04/27/2026QuenchA-frame can only hold 6-7 c-frame parts due to current arm length.Extend A-frame arm length to accomodate 4 c-frames per side.Lee / Omar / P&E07/30/2026Not Started
04/27/2026SolutionKnowledge gaps reducing 1st shift outputReview training plan and performance with solution/age operations team to identify modifications to current training and timeline.Lee S. / Andrea C.06/30/2026Not Started
04/27/2026Straightening150-press down causing excessive time waste from manually moving bed.Order double drum winch and modify rack & pinion indexing method to accommodate new cable style.DMC07/30/2026Not Started
04/27/2026All operationsScanners not readily available per process to scan shop travelersAdd scannersLee05/29/2026Not Started
04/27/2026All operationsProcess area naming breakdownPotential for breaking down order locations to give more accurate descriptionAndrea C.06/26/2026Complete
06/19/2026West Pre-InspectAdd wall pockets / Kanban for Pre-inspect priorityAdd wall pockets to make priority more visualAndrea / Gary07/06/2026Not Started

Status Overview

Status Colors

Not Started5
In Progress1
Complete2
On Hold0