| 04/27/2026 | Age | Excessive in process queue times | Review queue times, reasons, and opportunities with operations teams. | Lee S. | 07/31/2026 | In Progress | |
| 04/27/2026 | Quench | Hot water recovery time | DMC to install new boiler and test by 5/13 | Lee S. / DMC / Omar | 05/13/2026 | Complete | |
| 04/27/2026 | Quench | A-frame can only hold 6-7 c-frame parts due to current arm length. | Extend A-frame arm length to accomodate 4 c-frames per side. | Lee / Omar / P&E | 07/30/2026 | Not Started | |
| 04/27/2026 | Solution | Knowledge gaps reducing 1st shift output | Review training plan and performance with solution/age operations team to identify modifications to current training and timeline. | Lee S. / Andrea C. | 06/30/2026 | Not Started | |
| 04/27/2026 | Straightening | 150-press down causing excessive time waste from manually moving bed. | Order double drum winch and modify rack & pinion indexing method to accommodate new cable style. | DMC | 07/30/2026 | Not Started | |
| 04/27/2026 | All operations | Scanners not readily available per process to scan shop travelers | Add scanners | Lee | 05/29/2026 | Not Started | |
| 04/27/2026 | All operations | Process area naming breakdown | Potential for breaking down order locations to give more accurate description | Andrea C. | 06/26/2026 | Complete | |
| 06/19/2026 | West Pre-Inspect | Add wall pockets / Kanban for Pre-inspect priority | Add wall pockets to make priority more visual | Andrea / Gary | 07/06/2026 | Not Started | |